Notes:
5666 AC, 6989 SQ FT, SFR / 2 STORY
11/2/2003 12:00:00 AM
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
9. BEAMS=10"W X 26"D.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
51. "ASCE" REQUIRES TOP AND / OR BOTTOM BEAM REBAR PER 5.2.2.3 d.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
(11/2/2003 08:18 MBW)I-JOIST DRAWING REQUIRES ENGINEER SEAL & SIGNATURE.
CHIMNEY FRAME DESIGN REQUIRED.