Notes:
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
13. BEAMS=10"W X 32"D.
30. 1ST FLOOR WINDOW BOX-OUTS ONLY - AREA BOX-OUTS NOT ALLOWED.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
(1/28/2004 10:09 SOM)GRADE BEAMS - (2) #5 REBAR IN ALL BEAM BOTTOMS
MASONRY UNDER BOX-OUTS
REQUIRED GABLE (REAR ELEVATION)
MUST BE MASONRY(1/19/2004 10:57 SOM) ELECTRICAL CONTRACTOR NEEDS TO REGISTER
1930 AC, 2586 SQ FT, SFR / 1 STORY