Notes:
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
9. BEAMS=10"W X 26"D.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
59. INCLUDED IN THIS PERMIT PACK IS A DRAWING AND SPECIFICATION OF THE REQUIRED BARRIER-FREE RAMP.
(4/12/2004 08:59 SOM)3- #5 REBAR BOTTOM OF ALL BEAMS
SECOND FLOOR WITH 3-BEDROOMS, 2 BATHS, AND GAMEROOM
3363 AC, 4100 SQ FT, SFR \ 2 STORY