Notes:
4300 AC, 5334 SQ FT, SFR \ 2 STORY
7/7/2004 12:00:00 AM
REVERSE PLAN ON SAME LOT.
(6/25/2004 08:52 DEB)
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
24. EXITWAYS (HALLWAYS) MUST BE A MIN. 36"W INCLUDING ARCHED OR CASED OPENINGS. (TWO OR MORE ROOMS)
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
30. 1ST FLOOR WINDOW BOX-OUTS ONLY - AREA BOX-OUTS NOT ALLOWED.
31. SIDING OVER MASONRY AT SECOND STORY NOT ALLOWED.
32. SECOND FLOOR SIDING AREA MUST NOT EXCEED 50% OF THE TOTAL NET EXPOSED WALL AREA.
33. MEDIA ROOM WITH CLOTHES CLOSET MUST HAVE OPERABLE WINDOW.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
44. CO DETECTORS REQ'D ON ELECT LEGEND & ELECT PLAN 1/1000 SQ FT & 1 PER FLOOR MIN PLUS (1) ADD'L AT GARAGE ENTRY IN AC AREA.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
52. "J" GARAGE REQUIRES 28'0" FACE OF GARAGE TO SIDEYARD PROPERTY LINE.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
59. INCLUDED IN THIS PERMIT PACK IS A DRAWING AND SPECIFICATION OF THE REQUIRED BARRIER-FREE RAMP.
* BEAMS 8" X 31"
* 2ND STORY - 3 BDRMS, 2 BATHS, GAMEROOM AND MEDIA ROOM