Notes:
(06/30/2005 08:13 JC)
01. ***ENERGY STAR***
02. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
03. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
12. BEAMS=10"W X 30"D.
24. EXITWAYS (HALLWAYS) MUST BE A MIN. 36"W INCLUDING ARCHED OR CASED OPENINGS. (TWO OR MORE ROOMS)
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
33. MEDIA ROOM WITH CLOTHES CLOSET MUST HAVE OPERABLE WINDOW.
34. SIDING & TRIM MUST BE CEMENT FIBER OR ENGINEERED TREATED WOOD PRODUCT.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
(06/30/2005 08:13 JC)
Per builders plans and area summary - AC plus garage(s) are 5995 sf of area. Sprinkler system req'd. at 6000 sf of AC and garage(s).
5183A/C, 6611 SF, SFR / 2 STORY