Notes:
3219 AC, 3954 SF, SFR / 2 STORY
2/17/2006 12:00:00 AM
01. ***ENERGY STAR***
02. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
03. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
12. BEAMS=10"W X 30"D.
38. 1 HOUR FIRE WALL ASSEMBLY REQ'D - SUBMIT DESIGN PRIOR TO WALL CONSTRUCTION.
40. ON "0" SET-BACK SIDE OF HOUSE NO METERS OR VENTS ARE ALLOWED. GUTTER DOWNSPOUTS MUST DISCHARGE ONTO SAME PROPERTY 5'-0" FROM FOUNDATION.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
2 #4s IN THE BOTTOM OF ALL BEAMS WITHOUT BEAM STRANDS.
NOTE! EXTERIOR WALL OF MEDIA/BED ROOM #4 MUST BE 3' FROM THE "0" LINE OR BE 1 HOUR FIRE RATED.