Notes:
JM 6-13-08 3:30
PATIO COVERS:
PATIO COVERS SHALL COMPLY WITH THE CURRENT IRC APPENDIX H.
PLANS SHALL MATCH SITE CONSTRUCTION, PLANS TO REMAIN ON SITE THROUGHOUT CONSTRUCTION, NO EXCEPTIONS.
ALL WORK SUBJECT TO FIELD APPROVED INSPECTIONS AND TESTING.
PLEASE ATTACHED ACCESSORY STRUCTURE HANDOUT IN YOUR PERMIT PACKET,
A BRICK INSPECTION IS REQ'D. BEFORE COLUMNS ARE COVERED UP.
BRICK SHALL BE BROUGHT UP TO 4' AND THEN CALLED IN FOR INSPECTION. 22 GAUGE MINIMUM BRICK TIES SHALL BE USED, ONE BRICK TIE TO COVER 3.5 SQ.FT OF BRICK. INSPECTOR SHALL INSPECT SIMPSON BASE CONNECTION AT SLAB PRIOR TO BRICK.
INSPECTIONS REQ'D:
MISC. FRAME- ROOF MAY BE COMPLETE AT THIS INSPECTION, DO NOT APPLY SOFFIT OR CEILING UNTIL AFTER ROUGH FRAMING INSPECTION IS COMPLETE.
BRICK
MISC. BLDG. FINAL--SOFFIT AND/OR CEILING IS APPLIED AND ALL CONSTRUCTION IS COMPLETE
120 SQ FT, SADD / PATIO COVER